Transcon Ramdev Plaza, Santacruz West
Ready to move
by Transcon Iconica Private Limited · Santacruz West, Mumbai 400054 · Map
- Launched
- Aug 20176 yrs 4 mths originally promised
- Possession (MahaRERA)
- Apr 2027Extended by 3 yrs 4 mths
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 309 of 39977%
- Buildings
- 12.3 acres
- MahaRERA complaints
- 16Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale309 booked out of 399 units
Land-owner share49 units, not for sale
Total 448 units. Land-owner units are not for sale.
Project facts
- Other units
- 448
- Total units
- 448
- Buildings
- 1
- Land
- 2.3 acres
- Phases
- 1
- MahaRERA complaints
- 16
- Free-sale units
- 399
- Land-owner share (not for sale)
- 49
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 309 | |
| 100% | 100% | 30% | – | |
| 100% | 100% | 30% | – | |
| 100% | 100% | 30% | 260 |
"–" means MahaRERA shows no figure for that update.
About this project
Transcon Ramdev Plaza by Transcon Iconica Private Limited is a 448-unit SRA-sanctioned project in Santacruz West, Mumbai 400054, launched in August 2017 with possession due in April 2027. 309 units booked out of 399 units for sale. The concrete structure (RCC) is complete.
Read full summary
Transcon Ramdev Plaza is an SRA-sanctioned project by Transcon Iconica Private Limited in Santacruz West, Mumbai 400054, registered with MahaRERA as P51800010457. It was launched in August 2017. It has 448 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active. Of the 448 units, 399 are for sale and 49 are the land-owner's share, not for sale.
Its registered possession date is April 2027, extended by 3 years 4 months from the original December 2023. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
309 units booked out of 399 units for sale (77%). Since the July 2026 update, the possession date has moved from December 2024 to April 2027.
Transcon's track record in Mumbai
MahaRERA projects registered 2017–2024 in Mumbai
| Projects registered with MahaRERA | 14 |
|---|---|
| Total units across these projects | 4,175 |
| Completed without extending the possession date | 3 |
| Completed after an extension | 0 |
| Lapsed | 3 |
| Under construction | 8 |
| Possession date extended on the builder's application | 2 |
| Typical time from launch to 100% structure | 7 years 4 months |
| MahaRERA complaints (filed by or against the builder), all Transcon projects | 156 (13 of 14 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.