Alta Monte and Signet, Malad East

by Era Realtors Private Limited · Malad East, Mumbai 400097 · Map

Launched
Aug 20177 yrs 4 mths originally promised
Possession (MahaRERA)
Mar 2026Extended by 1 yr 3 mths
Concrete structure
100%Nearing possession
Booked
1,423 of 1,46297%
Buildings
52.7 acres
MahaRERA complaints
253Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
332
2 BHK
642
3 BHK
316
4 BHK
90
5+ BHK
36
Other units
46
Total units
1,462
Buildings
5
Land
2.7 acres
Phases
1
MahaRERA complaints
253

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services88%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 86%Dec 2025: Concrete structure (RCC) 86%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 14%Dec 2025: Final finishes 14%Jul 2026: Final finishes 88%Excavation 100%Concrete structure (RCC) 100%Final finishes 88%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%88%1,423
100%86%14%–
100%86%14%1,405

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Alta Monte and Signet by Era Realtors Private Limited is a 1,462-unit SRA-sanctioned project in Malad East, Mumbai 400097, launched in August 2017 with possession due in March 2026. 1,423 units booked out of total 1,462 units. The concrete structure (RCC) is complete.

Read full summary

Alta Monte and Signet is an SRA-sanctioned project by Era Realtors Private Limited in Malad East, Mumbai 400097, registered with MahaRERA as P51800010463. It was launched in August 2017. It has 1,462 units in 5 buildings: 1,416 homes (1, 2, 3, 4 and 5+ BHK) and 46 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Possession was due in March 2026, after an extension of 1 year 3 months from the original December 2024. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 88% complete.

1,423 units booked out of total 1,462 units (97%).