Alta Monte and Signet, Malad East
by Era Realtors Private Limited · Malad East, Mumbai 400097 · Map
- Launched
- Aug 20177 yrs 4 mths originally promised
- Possession (MahaRERA)
- Mar 2026Extended by 1 yr 3 mths
- Concrete structure
- 100%Nearing possession
- Booked
- 1,423 of 1,46297%
- Buildings
- 52.7 acres
- MahaRERA complaints
- 253Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 332
- 2 BHK
- 642
- 3 BHK
- 316
- 4 BHK
- 90
- 5+ BHK
- 36
- Other units
- 46
- Total units
- 1,462
- Buildings
- 5
- Land
- 2.7 acres
- Phases
- 1
- MahaRERA complaints
- 253
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 88% | 1,423 | |
| 100% | 86% | 14% | – | |
| 100% | 86% | 14% | 1,405 |
"–" means MahaRERA shows no figure for that update.
About this project
Alta Monte and Signet by Era Realtors Private Limited is a 1,462-unit SRA-sanctioned project in Malad East, Mumbai 400097, launched in August 2017 with possession due in March 2026. 1,423 units booked out of total 1,462 units. The concrete structure (RCC) is complete.
Read full summary
Alta Monte and Signet is an SRA-sanctioned project by Era Realtors Private Limited in Malad East, Mumbai 400097, registered with MahaRERA as P51800010463. It was launched in August 2017. It has 1,462 units in 5 buildings: 1,416 homes (1, 2, 3, 4 and 5+ BHK) and 46 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Possession was due in March 2026, after an extension of 1 year 3 months from the original December 2024. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 88% complete.
1,423 units booked out of total 1,462 units (97%).