Palai Towers, Goregaon West
by N D Developers · Goregaon West, Mumbai 400062 · Map
- Launched
- Aug 20173 yrs 10 mths originally promised
- Possession (MahaRERA)
- Apr 2027Extended by 5 yrs 10 mths
- Concrete structure
- 75%Mid-construction
- Booked
- 191 of 21788%
- Buildings
- 11.8 acres
- MahaRERA complaints
- 7Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 3 BHK
- 111
- 4 BHK
- 102
- Other units
- 4
- Total units
- 217
- Buildings
- 1
- Land
- 1.8 acres
- Phases
- 1
- MahaRERA complaints
- 7
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 75% | 40% | 191 | |
| 100% | 75% | 40% | 191 | |
| 100% | 75% | 30% | 189 | |
| 100% | 74% | 25% | 189 |
"–" means MahaRERA shows no figure for that update.
About this project
Palai Towers by N D Developers is a 217-unit BMC-sanctioned project in Goregaon West, Mumbai 400062, launched in August 2017 with possession due in April 2027. 191 units booked out of total 217 units. The concrete structure (RCC) is 75% complete.
Read full summary
Palai Towers is a BMC-sanctioned project by N D Developers in Goregaon West, Mumbai 400062, registered with MahaRERA as P51800010465. It was launched in August 2017. It has 217 units in 1 building: 213 homes (3 and 4 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is April 2027, extended by 5 years 10 months from the original June 2021. Construction: excavation complete, structure (RCC) 75% complete, final finishes 40% complete.
191 units booked out of total 217 units (88%).