Samarth Enclave F And G Wing Andheri Chhaya Chs, Andheri East
by Samarth Erectors And Developers · Andheri East, Mumbai 400093 · Map
- Launched
- Aug 20176 yrs 4 mths originally promised
- Possession (MahaRERA)
- Dec 2026Extended by 3 yrs
- Concrete structure
- 100%Nearing possession
- Booked
- 75 of 8291%
- Buildings
- 20.9 acres
- MahaRERA complaints
- 3Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 67
- 2 BHK
- 11
- Other units
- 4
- Total units
- 82
- Buildings
- 2
- Land
- 0.9 acres
- Phases
- 1
- MahaRERA complaints
- 3
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 98% | 100% | 80% | 75 | |
| 98% | 100% | 80% | 75 | |
| 97% | 100% | 0% | – | |
| 97% | 90% | 0% | 57 |
"–" means MahaRERA shows no figure for that update.
About this project
Samarth Enclave F And G Wing Andheri Chhaya Chs by Samarth Erectors And Developers is an 82-unit SRA-sanctioned project in Andheri East, Mumbai 400093, launched in August 2017 with possession due in December 2026. 75 units booked out of total 82 units. The concrete structure (RCC) is complete.
Read full summary
Samarth Enclave F And G Wing Andheri Chhaya Chs is an SRA-sanctioned project by Samarth Erectors And Developers in Andheri East, Mumbai 400093, registered with MahaRERA as P51800010790. It was launched in August 2017. It has 82 units in 2 buildings: 78 homes (1 and 2 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, extended by 3 years from the original December 2023. Construction: excavation 98% complete, structure (RCC) complete, final finishes 80% complete.
75 units booked out of total 82 units (91%).