Laxmi Nagar, Goregaon West
by Reliable Constructions · Goregaon West, Mumbai 400090 · Map
- Launched
- Aug 20176 yrs 4 mths originally promised
- Possession (MahaRERA)
- Apr 2027Extended by 3 yrs 4 mths
- Concrete structure
- 64%Mid-construction
- Booked (free sale)
- 202 of 29768%
- Buildings
- 61.8 acres
- MahaRERA complaints
- 19Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale202 booked out of 297 units
Land-owner share7 units, not for sale
Total 304 units. Land-owner units are not for sale.
Project facts
- 1 BHK
- 131
- 2 BHK
- 95
- 3 BHK
- 22
- 4 BHK
- 56
- Total units
- 304
- Buildings
- 6
- Land
- 1.8 acres
- Phases
- 1
- MahaRERA complaints
- 19
- Free-sale units
- 297
- Land-owner share (not for sale)
- 7
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 67% | 64% | 43% | 202 | |
| 67% | 64% | 43% | 202 | |
| 67% | 64% | 43% | 202 | |
| 67% | 64% | 43% | 156 |
"–" means MahaRERA shows no figure for that update.
About this project
Laxmi Nagar by Reliable Constructions is a 304-unit SRA-sanctioned project in Goregaon West, Mumbai 400090, launched in August 2017 with possession due in April 2027. 202 units booked out of 297 units for sale. The concrete structure (RCC) is 64% complete.
Read full summary
Laxmi Nagar is an SRA-sanctioned project by Reliable Constructions in Goregaon West, Mumbai 400090, registered with MahaRERA as P51800010918. It was launched in August 2017. It has 304 units in 6 buildings, with 1, 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 304 units, 297 are for sale and 7 are the land-owner's share, not for sale.
Its registered possession date is April 2027, extended by 3 years 4 months from the original December 2023. Construction: excavation 67% complete, structure (RCC) 64% complete, final finishes 43% complete.
202 units booked out of 297 units for sale (68%).