Skip to main content

Sanghvi Jewel, Malad West

by Sanghvi Realtors · Malad West, Mumbai 400064 · Map

Launched
Aug 20171 yr 4 mths originally promised
Possession (MahaRERA)
Apr 2027Extended by 8 yrs 4 mths
Concrete structure
90%Mid-construction
Booked
20 of 3754%
Buildings
20.5 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
37
Total units
37
Buildings
2
Land
0.5 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)90%
Finishes, lifts and services80%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 90%Dec 2025: Concrete structure (RCC) 90%Jul 2026: Concrete structure (RCC) 90%Oct 2026: Concrete structure (RCC) 90%Dec 2024: Final finishes 88%Dec 2025: Final finishes 80%Jul 2026: Final finishes 80%Oct 2026: Final finishes 80%Excavation 100%Concrete structure (RCC) 90%Final finishes 80%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%90%80%20
100%90%80%20
100%90%80%18
100%90%88%16

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Sanghvi Jewel by Sanghvi Realtors is a 37-unit BMC-sanctioned project in Malad West, Mumbai 400064, launched in August 2017 with possession due in April 2027. 20 units booked out of total 37 units. The concrete structure (RCC) is 90% complete.

Read full summary

Sanghvi Jewel is a BMC-sanctioned project by Sanghvi Realtors in Malad West, Mumbai 400064, registered with MahaRERA as P51800010958. It was launched in August 2017. It has 37 units in 2 buildings, as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is April 2027, extended by 8 years 4 months from the original December 2018. Construction: excavation complete, structure (RCC) 90% complete, final finishes 80% complete.

20 units booked out of total 37 units (54%).