Srishti Pride, Bhandup West

Ready to move

by Krishna Enterprise · Bhandup West, Mumbai 400078 · Map

Launched
Aug 2017First of 3 phases
Completed (MahaRERA)
Oct 2026Completion reported
Concrete structure
100%Weighted across 3 phases
Booked
–
Buildings
30.9 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
2
1 BHK
119
2 BHK
119
3 BHK
3
Total units
243
Buildings
3
Land
0.9 acres
Phases
3
MahaRERA complaints
0

The 3 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Srishti Pride Phase 1- Wing A
Completed
P5180001099481100%–
Srishti Pride Phase 2- Wing B
Completed
P5180002862982100%–
Srishti Pride Phase 3 - Wing C
Completed
P5180003261480100%–
Show updates by phase

Srishti Pride Phase 1- Wing A (P51800010994)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%99%–
100%100%99%–
100%100%99%79

"–" means MahaRERA shows no figure for that update.

Srishti Pride Phase 2- Wing B (P51800028629)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%99%–
100%100%99%–
100%100%99%78

"–" means MahaRERA shows no figure for that update.

Srishti Pride Phase 3 - Wing C (P51800032614)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%–
100%100%100%–
100%100%100%76

"–" means MahaRERA shows no figure for that update.

About this project

Srishti Pride by Krishna Enterprise is a 243-unit BMC-sanctioned project in Bhandup West, Mumbai 400078, launched in August 2017 and completed on MahaRERA (completion reported October 2026).

Read full summary

Srishti Pride is a BMC-sanctioned project by Krishna Enterprise in Bhandup West, Mumbai 400078, registered with MahaRERA as 3 phases (P51800010994, P51800028629, P51800032614). The first phase was launched in August 2017. Together the phases have 243 units in 3 buildings, with 1 RK, 1 BHK, 2 BHK and 3 BHK homes as registered with MahaRERA. All 3 phases are completed on MahaRERA.

All phases are completed on MahaRERA; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 99% complete. All 3 phases have their structure complete.