Serenity- Bldg 1, Powai

by JVPD Properties Private Limited · Powai, Mumbai 400076 · Map

Launched
Aug 20178 yrs 11 mths promised
Possession (MahaRERA)
Jul 2026Not extended
Concrete structure
0%Early stage
Booked
–
Buildings
10.1 acres
MahaRERA complaints
230Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
19
1 BHK
58
2 BHK
9
Total units
86
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
230

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation80%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 80%Dec 2025: Excavation 80%Jul 2026: Excavation 80%Oct 2026: Excavation 80%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 80%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
80%0%0%–
80%0%0%–
80%0%0%–
80%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Serenity- Bldg 1 by JVPD Properties Private Limited is an 86-unit project in Powai, Mumbai 400076, launched in August 2017 with possession due in July 2026. Work on the concrete structure (RCC) has not started.

Read full summary

Serenity- Bldg 1 is a project by JVPD Properties Private Limited in Powai, Mumbai 400076, registered with MahaRERA as P51800011181. It was launched in August 2017. It has 86 units in 1 building, with 1 RK, 1 BHK and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Possession was due in July 2026. That date has passed and no extension has been recorded. Construction: excavation 80% complete, structure (RCC) not started, final finishes not started.