Jaihind, Chembur

by S.P. Erectors And Developers Private Limited · Chembur, Mumbai 400071 · Map

Launched
Aug 20176 yrs 4 mths originally promised
Possession (MahaRERA)
Apr 2028Extended by 4 yrs 4 mths
Concrete structure
70%Mid-construction
Booked
83 of 15554%
Buildings
10.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
155
Total units
155
Buildings
1
Land
0.5 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation75%
Concrete structure (slabs)70%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 75%Dec 2025: Excavation 75%Jul 2026: Excavation 75%Oct 2026: Excavation 75%Dec 2024: Concrete structure (RCC) 70%Dec 2025: Concrete structure (RCC) 70%Jul 2026: Concrete structure (RCC) 70%Oct 2026: Concrete structure (RCC) 70%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 75%Concrete structure (RCC) 70%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
75%70%0%83
75%70%0%–
75%70%0%–
75%70%0%83

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Jaihind by S.P. Erectors And Developers Private Limited is a 155-unit SRA-sanctioned project in Chembur, Mumbai 400071, launched in August 2017 with possession due in April 2028. 83 units booked out of total 155 units. The concrete structure (RCC) is 70% complete.

Read full summary

Jaihind is an SRA-sanctioned project by S.P. Erectors And Developers Private Limited in Chembur, Mumbai 400071, registered with MahaRERA as P51800011367. It was launched in August 2017. It has 155 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is April 2028, extended by 4 years 4 months from the original December 2023. Construction: excavation 75% complete, structure (RCC) 70% complete, final finishes not started.

83 units booked out of total 155 units (54%).