Skip to main content

LEVEL - The Residences, Jogeshwari West

Ready to move

by M/s Siroya Keystone · Jogeshwari West, Mumbai 400102 · Map

Launched
Aug 20176 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2024Extended by 1 yr
Concrete structure
100%Ready to move
Booked
–
Buildings
11.3 acres
MahaRERA complaints
13Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Total units
–
Buildings
1
Land
1.3 acres
Phases
1
MahaRERA complaints
13

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services95%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 90%Dec 2025: Final finishes 95%Jul 2026: Final finishes 95%Excavation 100%Concrete structure (RCC) 100%Final finishes 95%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%–
100%100%95%–
100%100%90%211

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

LEVEL - The Residences by M/s Siroya Keystone is a project in Jogeshwari West, Mumbai 400102, launched in August 2017 with possession due in December 2024. The concrete structure (RCC) is complete.

Read full summary

LEVEL - The Residences is a project by M/s Siroya Keystone in Jogeshwari West, Mumbai 400102, registered with MahaRERA as P51800011428. It was launched in August 2017. Its MahaRERA status is Active.

Possession was due in December 2024, after an extension of 1 year from the original December 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.