Vicenza Residency/Commercial, Vikhroli

by Ssv Builders And Developers Pvt Ltd · Vikhroli, Mumbai 400083 · Map

Launched
Aug 201710 yrs 4 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
0%Early stage
Booked
2,160 of 2,160100%
Buildings
75.1 acres
MahaRERA complaints
15Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
450
2 BHK
1,640
Other units
70
Total units
2,160
Buildings
7
Land
5.1 acres
Phases
1
MahaRERA complaints
15

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation11%
Concrete structure (slabs)0%
Finishes, lifts and services4%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 11%Dec 2025: Excavation 11%Jul 2026: Excavation 11%Oct 2026: Excavation 11%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 4%Dec 2025: Final finishes 4%Jul 2026: Final finishes 4%Oct 2026: Final finishes 4%Excavation 11%Final finishes 4%Concrete structure (RCC) 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
11%0%4%2,160
11%0%4%–
11%0%4%–
11%0%4%2,160

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Vicenza Residency/Commercial by Ssv Builders And Developers Pvt Ltd is a 2,160-unit project in Vikhroli, Mumbai 400083, launched in August 2017 with possession due in December 2027. 2,160 units booked out of total 2,160 units. Work on the concrete structure (RCC) has not started.

Read full summary

Vicenza Residency/Commercial is a project by Ssv Builders And Developers Pvt Ltd in Vikhroli, Mumbai 400083, registered with MahaRERA as P51800011517. It was launched in August 2017. It has 2,160 units in 7 buildings: 2,090 homes (1 and 2 BHK) and 70 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation 11% complete, structure (RCC) not started, final finishes 4% complete.

2,160 units booked out of total 2,160 units (100%).