Skip to main content

Mobin Heights, Andheri West

Ready to move

by Gahlot Development Services Pvt Ltd · Andheri West, Mumbai 400058 · Map

Launched
Aug 20175 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2026Extended by 4 yrs
Concrete structure
100%Ready to move
Booked (free sale)
25 of 4260% · 4 rehab units
Buildings
10.6 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale25 booked out of 42 units

Rehab4 units for existing members

Land-owner share3 units, not for sale

Total 49 units. Rehab and land-owner units are not for sale.

Project facts

1 BHK
13
2 BHK
26
3 BHK
2
4 BHK
1
Other units
7
Total units
49
Buildings
1
Land
0.6 acres
Phases
1
MahaRERA complaints
0
Free-sale units
42
Rehab units
4
Land-owner share (not for sale)
3

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services98%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 25%Jul 2026: Final finishes 90%Oct 2026: Final finishes 98%Excavation 100%Concrete structure (RCC) 100%Final finishes 98%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%98%25
100%100%90%24
100%100%25%–
100%100%0%23

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400058

Projects with 20–90 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400058
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs 4 mths3 yrs 4 mths
Possession date extendedBy 4 yrs4 of 6
Possession date (MahaRERA)Dec 2026Mar 2024
Concrete structure (RCC)100%75%
Units booked (free sale)60%53%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Mobin Heights by Gahlot Development Services Pvt Ltd is a 49-unit BMC-sanctioned project in Andheri West, Mumbai 400058, launched in August 2017 with possession due in December 2026. 25 units booked out of 42 units for sale. The concrete structure (RCC) is complete.

Read full summary

Mobin Heights is a BMC-sanctioned project by Gahlot Development Services Pvt Ltd in Andheri West, Mumbai 400058, registered with MahaRERA as P51800011697. It was launched in August 2017. It has 49 units in 1 building: 42 homes (1, 2, 3 and 4 BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 49 units, 42 are for sale, 4 are rehab units for existing members and 3 are the land-owner's share, not for sale.

Its registered possession date is December 2026, extended by 4 years from the original December 2022. Construction: excavation complete, structure (RCC) complete, final finishes 98% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

25 units booked out of 42 units for sale (60%). Since the July 2026 update, 1 more unit has been booked.