Rolex SRA CHS, Jogeshwari East
by Square Constructions · Jogeshwari East, Mumbai 400060 · Map
- Launched
- Aug 20171 yr 7 mths originally promised
- Possession (MahaRERA)
- Mar 2020Extended by 1 yr
- Concrete structure
- 50%Mid-construction
- Booked (free sale)
- 65 of 8775% · 46 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale65 booked out of 87 units
Rehab46 units for existing members
Land-owner share6 units, not for sale
Total 139 units. Rehab and land-owner units are not for sale.
Project facts
- 1 BHK
- 111
- Other units
- 28
- Total units
- 139
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 87
- Rehab units
- 46
- Land-owner share (not for sale)
- 6
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 50% | 50% | 50% | 65 | |
| 50% | 50% | 50% | – | |
| 100% | 100% | 100% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Rolex SRA CHS by Square Constructions is a 139-unit SRA-sanctioned project in Jogeshwari East, Mumbai 400060, launched in August 2017 with possession due in March 2020. 65 units booked out of 87 units for sale. The concrete structure (RCC) is 50% complete.
Read full summary
Rolex SRA CHS is an SRA-sanctioned project by Square Constructions in Jogeshwari East, Mumbai 400060, registered with MahaRERA as P51800011887. It was launched in August 2017. It has 139 units in 1 building: 111 homes (1 BHK) and 28 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 139 units, 87 are for sale, 46 are rehab units for existing members and 6 are the land-owner's share, not for sale.
Possession was due in March 2020, after an extension of 1 year from the original March 2019. That date has passed and no further extension has been recorded. Construction: excavation 50% complete, structure (RCC) 50% complete, final finishes 50% complete.
65 units booked out of 87 units for sale (75%).