Mayur Tower, Bandra East

by Geopreneur Spire Realty · Bandra East, Mumbai 400051 · Map

Launched
Aug 20171 yr 7 mths originally promised
Possession (MahaRERA)
Apr 2027Extended by 8 yrs 1 mth
Concrete structure
100%Nearing possession
Booked (free sale)
52 of 6876% · 59 rehab units
Buildings
20.5 acres
MahaRERA complaints
10Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale52 booked out of 68 units

Rehab59 units for existing members

Total 127 units. Rehab units are not for sale.

Project facts

2 BHK
125
3 BHK
2
Total units
127
Buildings
2
Land
0.5 acres
Phases
1
MahaRERA complaints
10
Free-sale units
68
Rehab units
59

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services75%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 94%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 28%Dec 2025: Final finishes 75%Jul 2026: Final finishes 75%Oct 2026: Final finishes 75%Excavation 100%Concrete structure (RCC) 100%Final finishes 75%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%75%52
100%100%75%52
100%100%75%52
100%94%28%21

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Mayur Tower by Geopreneur Spire Realty is a 127-unit MHADA-sanctioned project in Bandra East, Mumbai 400051, launched in August 2017 with possession due in April 2027. 52 units booked out of 68 units for sale. The concrete structure (RCC) is complete.

Read full summary

Mayur Tower is a MHADA-sanctioned project by Geopreneur Spire Realty in Bandra East, Mumbai 400051, registered with MahaRERA as P51800011901. It was launched in August 2017. It has 127 units in 2 buildings, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 127 units, 68 are for sale and 59 are rehab units for existing members.

Its registered possession date is April 2027, extended by 8 years 1 month from the original March 2019. Construction: excavation complete, structure (RCC) complete, final finishes 75% complete.

52 units booked out of 68 units for sale (76%).