The Kollage, Andheri East

Ready to move

by Zire Rushi Construction · Andheri East, Mumbai 400069 · Map

Launched
Sep 20175 yrs 3 mths originally promised
Possession (MahaRERA)
Dec 2023Extended by 1 yr
Concrete structure
100%Ready to move
Booked
66 of 7390%
Buildings
10.7 acres
MahaRERA complaints
3Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
18
2 BHK
20
3 BHK
25
Other units
10
Total units
73
Buildings
1
Land
0.7 acres
Phases
1
MahaRERA complaints
3
Reserved units
9

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 75%Dec 2025: Final finishes 75%Jul 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%66
100%100%75%–
100%100%75%61

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

The Kollage by Zire Rushi Construction is a 73-unit BMC-sanctioned project in Andheri East, Mumbai 400069, launched in September 2017 with possession due in December 2023. 66 units booked out of total 73 units. The concrete structure (RCC) is complete.

Read full summary

The Kollage is a BMC-sanctioned project by Zire Rushi Construction in Andheri East, Mumbai 400069, registered with MahaRERA as P51800012084. It was launched in September 2017. It has 73 units in 1 building: 63 homes (1, 2 and 3 BHK) and 10 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Possession was due in December 2023, after an extension of 1 year from the original December 2022. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

66 units booked out of total 73 units (90%).