The Kollage, Andheri East
Ready to move
by Zire Rushi Construction · Andheri East, Mumbai 400069 · Map
- Launched
- Sep 20175 yrs 3 mths originally promised
- Possession (MahaRERA)
- Dec 2023Extended by 1 yr
- Concrete structure
- 100%Ready to move
- Booked
- 66 of 7390%
- Buildings
- 10.7 acres
- MahaRERA complaints
- 3Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 18
- 2 BHK
- 20
- 3 BHK
- 25
- Other units
- 10
- Total units
- 73
- Buildings
- 1
- Land
- 0.7 acres
- Phases
- 1
- MahaRERA complaints
- 3
- Reserved units
- 9
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 66 | |
| 100% | 100% | 75% | – | |
| 100% | 100% | 75% | 61 |
"–" means MahaRERA shows no figure for that update.
About this project
The Kollage by Zire Rushi Construction is a 73-unit BMC-sanctioned project in Andheri East, Mumbai 400069, launched in September 2017 with possession due in December 2023. 66 units booked out of total 73 units. The concrete structure (RCC) is complete.
Read full summary
The Kollage is a BMC-sanctioned project by Zire Rushi Construction in Andheri East, Mumbai 400069, registered with MahaRERA as P51800012084. It was launched in September 2017. It has 73 units in 1 building: 63 homes (1, 2 and 3 BHK) and 10 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Possession was due in December 2023, after an extension of 1 year from the original December 2022. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
66 units booked out of total 73 units (90%).