Center Court, Mulund West
by Ricardo Constructions Private Limited · Mulund West, Mumbai 400080 · Map
- Launched
- Sep 20178 yrs 3 mths originally promised
- Possession (MahaRERA)
- Aug 2028Extended by 2 yrs 8 mths
- Concrete structure
- 0%Early stage
- Booked
- 18 of 15512%
- Buildings
- 11.6 acres
- MahaRERA complaints
- 10Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 80
- 3 BHK
- 75
- Total units
- 155
- Buildings
- 1
- Land
- 1.6 acres
- Phases
- 1
- MahaRERA complaints
- 10
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Work not started as of Oct 2026
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 0% | 0% | 18 | |
| 0% | 0% | 0% | 18 | |
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | 18 |
"–" means MahaRERA shows no figure for that update.
About this project
Center Court by Ricardo Constructions Private Limited is a 155-unit BMC-sanctioned project in Mulund West, Mumbai 400080, launched in September 2017 with possession due in August 2028. 18 units booked out of total 155 units. Work on the concrete structure (RCC) has not started.
Read full summary
Center Court is a BMC-sanctioned project by Ricardo Constructions Private Limited in Mulund West, Mumbai 400080, registered with MahaRERA as P51800012386. It was launched in September 2017. It has 155 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is August 2028, extended by 2 years 8 months from the original December 2025. Construction: excavation not started, structure (RCC) not started, final finishes not started.
18 units booked out of total 155 units (12%).
Ricardo's track record in Mumbai
MahaRERA projects registered 2017–2017 in Mumbai
| Projects registered with MahaRERA | 3 |
|---|---|
| Total units across these projects | 912 |
| Completed without extending the possession date | 0 |
| Completed after an extension | 0 |
| Lapsed | 0 |
| Under construction | 3 |
| Possession date extended on the builder's application | 3 |
| MahaRERA complaints (filed by or against the builder), all Ricardo projects | 170 (3 of 3 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.