Avalon Residency Tower - 4, Goregaon West
by Avalon Residency LLP · Goregaon West, Mumbai 400062 · Map
- Launched
- Sep 20175 yrs 7 mths originally promised
- Possession (MahaRERA)
- Jan 2030Extended by 6 yrs 9 mths
- Concrete structure
- 13%Mid-construction
- Booked (free sale)
- 1 of 617% · 6 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale1 booked out of 6 units
Rehab6 units for existing members
Total 12 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 9
- 2 BHK
- 3
- Total units
- 12
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 6
- Rehab units
- 6
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 13% | 0% | 1 | |
| 100% | 0% | 0% | 0 | |
| 90% | 0% | 0% | 0 | |
| 100% | 10% | 0% | 10 |
"–" means MahaRERA shows no figure for that update.
About this project
Avalon Residency Tower - 4 by Avalon Residency LLP is a 12-unit BMC-sanctioned project in Goregaon West, Mumbai 400062, launched in September 2017 with possession due in January 2030. 1 unit booked out of 6 units for sale. The concrete structure (RCC) is 13% complete.
Read full summary
Avalon Residency Tower - 4 is a BMC-sanctioned project by Avalon Residency LLP in Goregaon West, Mumbai 400062, registered with MahaRERA as P51800012980. It was launched in September 2017. It has 12 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 12 units, 6 are for sale and 6 are rehab units for existing members.
Its registered possession date is January 2030, extended by 6 years 9 months from the original April 2023. Construction: excavation complete, structure (RCC) 13% complete, final finishes not started.
1 unit booked out of 6 units for sale (17%). Since the July 2026 update, 1 more unit has been booked and the reported concrete structure (RCC) has gone from 0% to 13%.