Skip to main content

United Elicas, Chembur

by II Walls Infra LLP · Chembur, Mumbai 400071 · Map

Launched
Sep 20177 yrs 3 mths originally promised
Possession (MahaRERA)
Jul 2027Extended by 2 yrs 7 mths
Concrete structure
100%Nearing possession
Booked
14 of 2948% · 15 in Jul 2026
Buildings
10.1 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
19
2 BHK
10
Total units
29
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 85%Dec 2025: Concrete structure (RCC) 82%Jul 2026: Concrete structure (RCC) 82%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%14
100%82%0%15
100%82%0%–
100%85%0%15

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400071

Projects with 10–60 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400071
MeasureThis projectSimilar projects
Launch to possession (as first promised)7 yrs 3 mths4 yrs 4 mths
Possession date extendedBy 2 yrs 7 mths4 of 6
Possession date (MahaRERA)Jul 2027Dec 2025
Concrete structure (RCC)100%84%
Units booked48%57%
MahaRERA complaints (filed by or against the builder)14

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

United Elicas by II Walls Infra LLP is a 29-unit SRA-sanctioned project in Chembur, Mumbai 400071, launched in September 2017 with possession due in July 2027. 14 units booked out of total 29 units. The concrete structure (RCC) is complete.

Read full summary

United Elicas is an SRA-sanctioned project by II Walls Infra LLP in Chembur, Mumbai 400071, registered with MahaRERA as P51800013015. It was launched in September 2017. It has 29 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is July 2027, extended by 2 years 7 months from the original December 2024. Construction: excavation complete, structure (RCC) complete, final finishes not started.

14 units booked out of total 29 units (48%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 82% to 100% and the possession date has moved from December 2025 to July 2027.