Phoenix Heights, Andheri West

by Mohid Construction Co · Andheri West, Mumbai 400053 · Map

Launched
Sep 20177 yrs originally promised
Possession (MahaRERA)
Dec 2029Extended by 5 yrs 3 mths
Concrete structure
12%Mid-construction
Booked (free sale)
18 of 18710% · 9 rehab units
Buildings
10.3 acres
MahaRERA complaints
3Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale18 booked out of 187 units

Rehab9 units for existing members

Total 196 units. Rehab units are not for sale.

Project facts

Other units
196
Total units
196
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
3
Free-sale units
187
Rehab units
9

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)12%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Jul 2026Oct 2026Dec 2024: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 12%Dec 2024: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 12%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%12%0%18
100%0%0%50
100%0%0%41

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Phoenix Heights by Mohid Construction Co is a 196-unit SRA-sanctioned project in Andheri West, Mumbai 400053, launched in September 2017 with possession due in December 2029. 18 units booked out of 187 units for sale. The concrete structure (RCC) is 12% complete.

Read full summary

Phoenix Heights is an SRA-sanctioned project by Mohid Construction Co in Andheri West, Mumbai 400053, registered with MahaRERA as P51800013366. It was launched in September 2017. It has 196 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active. Of the 196 units, 187 are for sale and 9 are rehab units for existing members.

Its registered possession date is December 2029, extended by 5 years 3 months from the original September 2024. Construction: excavation complete, structure (RCC) 12% complete, final finishes not started.

18 units booked out of 187 units for sale (10%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 12%.