- Launched
- Oct 20174 yrs 2 mths originally promised
- Possession (MahaRERA)
- Dec 2027Extended by 6 yrs
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 12 of 2157% · 13 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale12 booked out of 21 units
Rehab13 units for existing members
Total 34 units. Rehab units are not for sale.
Project facts
- 1 RK
- 8
- 1 BHK
- 8
- 2 BHK
- 18
- Total units
- 34
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 21
- Rehab units
- 13
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 97% | 12 | |
| 100% | 100% | 97% | 10 | |
| 100% | 100% | 97% | – | |
| 100% | 100% | 97% | 4 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400058
Projects with 10–70 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 2 mths | 3 yrs 4 mths |
| Possession date extended | By 6 yrs | 4 of 4 |
| Possession date (MahaRERA) | Dec 2027 | Feb 2024 |
| Concrete structure (RCC) | 100% | 65% |
| Units booked (free sale) | 57% | 58% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Fairmont Moksh, Andheri West
- Shanta Mangesh Apartment, Andheri West
- Forefront Northeast-100, Andheri West
- La Alteza, Andheri West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Fairmont Moksh | August 2017 | December 2020 | 30% | 4 units booked out of total 30 units |
| Shanta Mangesh Apartment | August 2017 | December 2019 | 100% | – |
| Forefront Northeast-100 | August 2017 | April 2029 | 0% | 7 units booked out of 12 units for sale |
| La Alteza | August 2017 | April 2027 | 100% | 50 units booked out of total 69 units |
About this project
Sai Darshan by Shah Patel & Co is a 34-unit BMC-sanctioned project in Andheri West, Mumbai 400058, launched in October 2017 with possession due in December 2027. 12 units booked out of 21 units for sale. The concrete structure (RCC) is complete.
Read full summary
Sai Darshan is a BMC-sanctioned project by Shah Patel & Co in Andheri West, Mumbai 400058, registered with MahaRERA as P51800013711. It was launched in October 2017. It has 34 units in 1 building, with 1 RK, 1 BHK and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 34 units, 21 are for sale and 13 are rehab units for existing members.
Its registered possession date is December 2027, extended by 6 years from the original December 2021. Construction: excavation complete, structure (RCC) complete, final finishes 97% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
12 units booked out of 21 units for sale (57%). Since the July 2026 update, 2 more units have been booked and the possession date has moved from December 2022 to December 2027.