Prem Builders, Jogeshwari East

Ready to move

by Prem Builders · Jogeshwari East, Mumbai 400060 · Map

Launched
Nov 20176 yrs 11 mths originally promised
Possession (MahaRERA)
Oct 2026Extended by 2 yrs
Concrete structure
100%Ready to move
Booked
218 of 32168% · 162 in Jul 2026
Buildings
11.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
321
Total units
321
Buildings
1
Land
1.5 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation90%
Concrete structure (slabs)100%
Finishes, lifts and services90%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 90%Dec 2025: Excavation 90%Jul 2026: Excavation 90%Oct 2026: Excavation 90%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 65%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 55%Oct 2026: Final finishes 90%Concrete structure (RCC) 100%Excavation 90%Final finishes 90%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
90%100%90%218
90%100%55%162
90%65%0%92
90%0%0%17

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Prem Builders by Prem Builders is a 321-unit SRA-sanctioned project in Jogeshwari East, Mumbai 400060, launched in November 2017 with possession due in October 2026. 218 units booked out of total 321 units. The concrete structure (RCC) is complete.

Read full summary

Prem Builders is an SRA-sanctioned project by Prem Builders in Jogeshwari East, Mumbai 400060, registered with MahaRERA as P51800013919. It was launched in November 2017. It has 321 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is October 2026, extended by 2 years from the original October 2024. Construction: excavation 90% complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

218 units booked out of total 321 units (68%). Since the July 2026 update, 56 more units have been booked.