by Tanvi Construction Pvt Ltd · Dahisar, Mumbai 400068 · Map

Launched
Nov 20177 yrs 1 mth originally promised
Possession (MahaRERA)
Apr 2029Extended by 4 yrs 4 mths
Concrete structure
75%Mid-construction
Booked
135 of 17577% · 134 in Jul 2026
Buildings
12.8 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
175
Total units
175
Buildings
1
Land
2.8 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)75%
Finishes, lifts and services75%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 70%Dec 2025: Excavation 70%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 75%Oct 2026: Concrete structure (RCC) 75%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 75%Oct 2026: Final finishes 75%Excavation 100%Concrete structure (RCC) 75%Final finishes 75%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%75%75%135
100%75%75%134
70%0%0%135
70%0%0%61

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

The Platina by Tanvi Construction Pvt Ltd is a 175-unit project in Dahisar, Mumbai 400068, launched in November 2017 with possession due in April 2029. 135 units booked out of total 175 units. The concrete structure (RCC) is 75% complete.

Read full summary

The Platina is a project by Tanvi Construction Pvt Ltd in Dahisar, Mumbai 400068, registered with MahaRERA as P51800014131. It was launched in November 2017. It has 175 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is April 2029, extended by 4 years 4 months from the original December 2024. Construction: excavation complete, structure (RCC) 75% complete, final finishes 75% complete.

135 units booked out of total 175 units (77%). Since the July 2026 update, 1 more unit has been booked and the possession date has moved from March 2026 to April 2029.