by Nirvaana Constructions LLP · Vikhroli, Mumbai 400083 · Map

Launched
Nov 20176 yrs 7 mths originally promised
Possession (MahaRERA)
Jun 2027Extended by 3 yrs
Concrete structure
80%Mid-construction
Booked
26 of 10325%
Buildings
10.3 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
31
2 BHK
60
Other units
12
Total units
103
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)80%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 45%Dec 2025: Concrete structure (RCC) 75%Jul 2026: Concrete structure (RCC) 80%Oct 2026: Concrete structure (RCC) 80%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 80%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%80%0%26
100%80%0%–
100%75%0%–
100%45%0%26

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Nirvaana Heights by Nirvaana Constructions LLP is a 103-unit MHADA-sanctioned project in Vikhroli, Mumbai 400083, launched in November 2017 with possession due in June 2027. 26 units booked out of total 103 units. The concrete structure (RCC) is 80% complete.

Read full summary

Nirvaana Heights is a MHADA-sanctioned project by Nirvaana Constructions LLP in Vikhroli, Mumbai 400083, registered with MahaRERA as P51800014340. It was launched in November 2017. It has 103 units in 1 building: 91 homes (1 and 2 BHK) and 12 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2027, extended by 3 years from the original June 2024. Construction: excavation complete, structure (RCC) 80% complete, final finishes not started.

26 units booked out of total 103 units (25%).