Skip to main content

Veer Siddhanak Chs Ltd, Kurla East

Ready to move

by Om Sai Griha Nirman Pvt Ltd · Kurla East, Mumbai 400024 · Map

Launched
Feb 20184 yrs 11 mths originally promised
Possession (MahaRERA)
Dec 2026Extended by 3 yrs 11 mths
Concrete structure
100%Ready to move
Booked
37 of 4582% · 36 in Jul 2026
Buildings
10.4 acres
MahaRERA complaints
2Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
3
2 BHK
36
Other units
6
Total units
45
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
2

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 33%Dec 2025: Final finishes 90%Jul 2026: Final finishes 100%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%37
100%100%100%36
100%100%90%36
100%100%33%33

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Veer Siddhanak Chs Ltd by Om Sai Griha Nirman Pvt Ltd is a 45-unit BMC-sanctioned project in Kurla East, Mumbai 400024, launched in February 2018 with possession due in December 2026. 37 units booked out of total 45 units. The concrete structure (RCC) is complete.

Read full summary

Veer Siddhanak Chs Ltd is a BMC-sanctioned project by Om Sai Griha Nirman Pvt Ltd in Kurla East, Mumbai 400024, registered with MahaRERA as P51800015156. It was launched in February 2018. It has 45 units in 1 building: 39 homes (1 and 2 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, extended by 3 years 11 months from the original January 2023. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

37 units booked out of total 45 units (82%). Since the July 2026 update, 1 more unit has been booked and the possession date has moved from December 2023 to December 2026.