Sky Annex, Chembur
by Stans Buildtech Homes Private Limited · Chembur, Mumbai 400074 · Map
- Launched
- Feb 20185 yrs 10 mths originally promised
- Possession (MahaRERA)
- Apr 2029Extended by 5 yrs 4 mths
- Concrete structure
- 15%Mid-construction
- Booked
- 193 of 35355%
- Buildings
- 11.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 218
- 2 BHK
- 70
- 3 BHK
- 65
- Total units
- 353
- Buildings
- 1
- Land
- 1.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 15% | 0% | 193 | |
| 100% | 15% | 0% | 193 | |
| 100% | 15% | 0% | 193 | |
| 0% | 0% | 0% | 38 |
"–" means MahaRERA shows no figure for that update.
About this project
Sky Annex by Stans Buildtech Homes Private Limited is a 353-unit SRA-sanctioned project in Chembur, Mumbai 400074, launched in February 2018 with possession due in April 2029. 193 units booked out of total 353 units. The concrete structure (RCC) is 15% complete.
Read full summary
Sky Annex is an SRA-sanctioned project by Stans Buildtech Homes Private Limited in Chembur, Mumbai 400074, registered with MahaRERA as P51800015214. It was launched in February 2018. It has 353 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is April 2029, extended by 5 years 4 months from the original December 2023. Construction: excavation complete, structure (RCC) 15% complete, final finishes not started.
193 units booked out of total 353 units (55%).
Stans Buildtech's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 7 |
|---|---|
| Total units across these projects | 1,323 |
| Completed without extending the possession date | 1 |
| Completed after an extension | 0 |
| Lapsed | 2 |
| Under construction | 4 |
| Possession date extended on the builder's application | 2 |
| MahaRERA complaints (filed by or against the builder), all Stans Buildtech projects | 3 (2 of 7 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.