Shree Manik Vishwa, Dahisar
by Anil Gangaram Sawant · Dahisar, Mumbai 400068 · Map
- Launched
- Feb 20184 yrs 6 mths originally promised
- Possession (MahaRERA)
- Apr 2028Extended by 5 yrs 8 mths
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 48 of 5686% · 11 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale48 booked out of 56 units
Rehab11 units for existing members
Total 67 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 17
- 2 BHK
- 34
- Other units
- 16
- Total units
- 67
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 56
- Rehab units
- 11
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 15% | 48 | |
| 100% | 100% | 15% | 46 | |
| 0% | 0% | 0% | 42 | |
| 0% | 0% | 0% | 26 |
"–" means MahaRERA shows no figure for that update.
About this project
Shree Manik Vishwa by Anil Gangaram Sawant is a 67-unit BMC-sanctioned project in Dahisar, Mumbai 400068, launched in February 2018 with possession due in April 2028. 48 units booked out of 56 units for sale. The concrete structure (RCC) is complete.
Read full summary
Shree Manik Vishwa is a BMC-sanctioned project by Anil Gangaram Sawant in Dahisar, Mumbai 400068, registered with MahaRERA as P51800015282. It was launched in February 2018. It has 67 units in 1 building: 51 homes (1 and 2 BHK) and 16 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 67 units, 56 are for sale and 11 are rehab units for existing members.
Its registered possession date is April 2028, extended by 5 years 8 months from the original August 2022. Construction: excavation complete, structure (RCC) complete, final finishes 15% complete.
48 units booked out of 56 units for sale (86%). Since the July 2026 update, 2 more units have been booked and the possession date has moved from August 2023 to April 2028.