Gulab Mansion, Sion

by Jyotindrakumar Punamchand Shah · Sion, Mumbai 400022 · Map

Launched
Mar 20182 yrs originally promised
Possession (MahaRERA)
Dec 2027Extended by 7 yrs 9 mths
Concrete structure
54%Mid-construction
Booked
–
Buildings
11.1 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
7
Total units
7
Buildings
1
Land
1.1 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)54%
Finishes, lifts and services80%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 54%Dec 2025: Concrete structure (RCC) 54%Jul 2026: Concrete structure (RCC) 54%Oct 2026: Concrete structure (RCC) 54%Dec 2024: Final finishes 80%Dec 2025: Final finishes 80%Jul 2026: Final finishes 80%Oct 2026: Final finishes 80%Excavation 100%Final finishes 80%Concrete structure (RCC) 54%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%54%80%–
100%54%80%–
100%54%80%–
100%54%80%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Gulab Mansion by Jyotindrakumar Punamchand Shah is a 7-unit project in Sion, Mumbai 400022, launched in March 2018 with possession due in December 2027. The concrete structure (RCC) is 54% complete.

Read full summary

Gulab Mansion is a project by Jyotindrakumar Punamchand Shah in Sion, Mumbai 400022, registered with MahaRERA as P51800015543. It was launched in March 2018. It has 7 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, extended by 7 years 9 months from the original March 2020. Construction: excavation complete, structure (RCC) 54% complete, final finishes 80% complete.