Skip to main content

Nahid Heights, Malad East

Ready to move

by M/S Nahid Enterprises · Malad East, Mumbai 400097 · Map

Launched
Mar 20184 yrs 9 mths originally promised
Possession (MahaRERA)
Dec 2026Extended by 4 yrs
Concrete structure
100%Ready to move
Booked
22 of 3073%
Buildings
10.1 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
2
1 BHK
14
2 BHK
8
3 BHK
1
Other units
5
Total units
30
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
1
Reserved units
2

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 75%Dec 2025: Final finishes 75%Jul 2026: Final finishes 100%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%22
100%100%100%22
100%100%75%–
100%100%75%12

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Nahid Heights by M/S Nahid Enterprises is a 30-unit BMC-sanctioned project in Malad East, Mumbai 400097, launched in March 2018 with possession due in December 2026. 22 units booked out of total 30 units. The concrete structure (RCC) is complete.

Read full summary

Nahid Heights is a BMC-sanctioned project by M/S Nahid Enterprises in Malad East, Mumbai 400097, registered with MahaRERA as P51800015811. It was launched in March 2018. It has 30 units in 1 building: 25 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 5 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, extended by 4 years from the original December 2022. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

22 units booked out of total 30 units (73%).