Kalpvruksh, Kandivali West

by Ikira Build Tech LLP · Kandivali West, Mumbai 400067 · Map

Launched
Apr 20183 yrs 2 mths originally promised
Possession (MahaRERA)
Apr 2027Extended by 5 yrs 10 mths
Concrete structure
0%Early stage
Booked (free sale)
7 of 3719% · 12 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale7 booked out of 37 units

Rehab12 units for existing members

Total 49 units. Rehab units are not for sale.

Project facts

1 RK
4
1 BHK
38
2 BHK
7
Total units
49
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
37
Rehab units
12

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation50%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 50%Dec 2025: Excavation 0%Jul 2026: Excavation 0%Oct 2026: Excavation 50%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 50%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
50%0%0%7
0%0%0%0
0%0%0%0
50%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400067

Projects with 20–100 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400067
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 2 mths2 yrs 11 mths
Possession date extendedBy 5 yrs 10 mths3 of 3
Possession date (MahaRERA)Apr 2027Dec 2025
Concrete structure (RCC)0%64%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Kalpvruksh by Ikira Build Tech LLP is a 49-unit BMC-sanctioned project in Kandivali West, Mumbai 400067, launched in April 2018 with possession due in April 2027. 7 units booked out of 37 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Kalpvruksh is a BMC-sanctioned project by Ikira Build Tech LLP in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800016023. It was launched in April 2018. It has 49 units in 1 building, with 1 RK, 1 BHK and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 49 units, 37 are for sale and 12 are rehab units for existing members.

Its registered possession date is April 2027, extended by 5 years 10 months from the original June 2021. Construction: excavation 50% complete, structure (RCC) not started, final finishes not started.

7 units booked out of 37 units for sale (19%). Since the July 2026 update, 7 more units have been booked and the possession date has moved from December 2024 to April 2027.