Business Bay, Andheri East

by Ritu Multitrade Services Pvt Ltd · Andheri East, Mumbai 400093 · Map

Launched
Jun 20187 yrs 6 mths originally promised
Possession (MahaRERA)
Dec 2030Extended by 5 yrs
Concrete structure
80%Mid-construction
Booked
6 of 2524%
Buildings
10.6 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
25
Total units
25
Buildings
1
Land
0.6 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)80%
Finishes, lifts and services75%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 40%Dec 2025: Concrete structure (RCC) 80%Jul 2026: Concrete structure (RCC) 80%Oct 2026: Concrete structure (RCC) 80%Dec 2024: Final finishes 70%Dec 2025: Final finishes 75%Jul 2026: Final finishes 75%Oct 2026: Final finishes 75%Excavation 100%Concrete structure (RCC) 80%Final finishes 75%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%80%75%6
100%80%75%–
100%80%75%–
100%40%70%6

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Business Bay by Ritu Multitrade Services Pvt Ltd is a 25-unit MMRDA-sanctioned project in Andheri East, Mumbai 400093, launched in June 2018 with possession due in December 2030. 6 units booked out of total 25 units. The concrete structure (RCC) is 80% complete.

Read full summary

Business Bay is an MMRDA-sanctioned project by Ritu Multitrade Services Pvt Ltd in Andheri East, Mumbai 400093, registered with MahaRERA as P51800016955. It was launched in June 2018. It has 25 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2030, extended by 5 years from the original December 2025. Construction: excavation complete, structure (RCC) 80% complete, final finishes 75% complete.

6 units booked out of total 25 units (24%).