Aurigae Residency D Wing, Kandivali East
Ready to move
by Adinathay · Kandivali East, Mumbai 400101 · Map
- Launched
- Jan 20195 yrs 11 mths originally promised
- Possession (MahaRERA)
- Mar 2027Extended by 2 yrs 3 mths
- Concrete structure
- 100%Ready to move
- Booked
- 74 of 8092% · 73 in Jul 2026
- Buildings
- 11.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 19
- 2 BHK
- 61
- Total units
- 80
- Buildings
- 1
- Land
- 1.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 74 | |
| 0% | 0% | 0% | 73 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Aurigae Residency D Wing by Adinathay is an 80-unit BMC-sanctioned project in Kandivali East, Mumbai 400101, launched in January 2019 with possession due in March 2027. 74 units booked out of total 80 units. The concrete structure (RCC) is complete.
Read full summary
Aurigae Residency D Wing is a BMC-sanctioned project by Adinathay in Kandivali East, Mumbai 400101, registered with MahaRERA as P51800019096. It was launched in January 2019. It has 80 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is March 2027, extended by 2 years 3 months from the original December 2024. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
74 units booked out of total 80 units (92%). Since the July 2026 update, 1 more unit has been booked, the reported concrete structure (RCC) has gone from 0% to 100% and the possession date has moved from December 2024 to March 2027.