I Wing Samarth Enclave Andheri Chhaya CHS, Andheri East

by Samarth Erectors And Developers · Andheri East, Mumbai 400093 · Map

Launched
Jan 20195 yrs 2 mths originally promised
Possession (MahaRERA)
Jun 2029Extended by 5 yrs 3 mths
Concrete structure
0%Early stage
Booked
21 of 4646%
Buildings
10.1 acres
MahaRERA complaints
4Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
39
Other units
7
Total units
46
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
4
Reserved units
2

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation60%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 0%Jul 2026: Excavation 60%Oct 2026: Excavation 60%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 60%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
60%0%0%21
60%0%0%21
0%0%0%–
0%0%0%22

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

I Wing Samarth Enclave Andheri Chhaya CHS by Samarth Erectors And Developers is a 46-unit SRA-sanctioned project in Andheri East, Mumbai 400093, launched in January 2019 with possession due in June 2029. 21 units booked out of total 46 units. Work on the concrete structure (RCC) has not started.

Read full summary

I Wing Samarth Enclave Andheri Chhaya CHS is an SRA-sanctioned project by Samarth Erectors And Developers in Andheri East, Mumbai 400093, registered with MahaRERA as P51800019223. It was launched in January 2019. It has 46 units in 1 building: 39 homes (2 BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2029, extended by 5 years 3 months from the original March 2024. Construction: excavation 60% complete, structure (RCC) not started, final finishes not started.

21 units booked out of total 46 units (46%).