Sudhanshu Heights, Bhandup East
Ready to move
by Sudhanshu Infrastructures Pvt Ltd · Bhandup East, Mumbai 400042 · Map
- Launched
- Jan 20193 yrs 5 mths originally promised
- Possession (MahaRERA)
- Mar 2027Extended by 4 yrs 9 mths
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 21 of 21100% · 29 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale21 booked out of 21 units
Rehab29 units for existing members
Total 50 units. Rehab units are not for sale.
Project facts
- 1 RK
- 1
- 1 BHK
- 23
- 2 BHK
- 19
- Other units
- 7
- Total units
- 50
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 21
- Rehab units
- 29
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 90% | 21 | |
| 100% | 100% | 0% | – | |
| 100% | 100% | 0% | – | |
| 100% | 100% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Sudhanshu Heights by Sudhanshu Infrastructures Pvt Ltd is a 50-unit BMC-sanctioned project in Bhandup East, Mumbai 400042, launched in January 2019 with possession due in March 2027. 21 units booked out of 21 units for sale. The concrete structure (RCC) is complete.
Read full summary
Sudhanshu Heights is a BMC-sanctioned project by Sudhanshu Infrastructures Pvt Ltd in Bhandup East, Mumbai 400042, registered with MahaRERA as P51800019314. It was launched in January 2019. It has 50 units in 1 building: 43 homes (1 RK, 1 BHK and 2 BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 50 units, 21 are for sale and 29 are rehab units for existing members.
Its registered possession date is March 2027, extended by 4 years 9 months from the original June 2022. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
21 units booked out of 21 units for sale (100%). Since the July 2026 update, the possession date has moved from June 2023 to March 2027.