Paradigm Antalya, Jogeshwari West
by Gajaanan Property Developers Private Limited · Jogeshwari West, Mumbai 400102 · Map
- Launched
- Mar 201917 yrs 9 mths promised
- Possession (MahaRERA)
- Dec 2036Not extended
- Concrete structure
- 5%Mid-construction
- Booked
- 684 of 3,83918%
- Buildings
- 206.5 acres
- MahaRERA complaints
- 69Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 RK
- 3
- 1 BHK
- 2,351
- 2 BHK
- 1,273
- Other units
- 212
- Total units
- 3,839
- Buildings
- 20
- Land
- 6.5 acres
- Phases
- 1
- MahaRERA complaints
- 69
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 6% | 5% | 0% | 684 | |
| 6% | 5% | 0% | – | |
| 6% | 5% | 0% | – | |
| 6% | 5% | 0% | 684 |
"–" means MahaRERA shows no figure for that update.
About this project
Paradigm Antalya by Gajaanan Property Developers Private Limited (Paradigm) is a 3,839-unit SRA-sanctioned project in Jogeshwari West, Mumbai 400102, launched in March 2019 with possession due in December 2036. 684 units booked out of total 3,839 units. The concrete structure (RCC) is 5% complete.
Read full summary
Paradigm Antalya is an SRA-sanctioned project by Gajaanan Property Developers Private Limited in Jogeshwari West, Mumbai 400102, registered with MahaRERA as P51800020208. It was launched in March 2019. It has 3,839 units in 20 buildings: 3,627 homes (1 RK, 1 BHK and 2 BHK) and 212 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2036, unchanged since launch. Construction: excavation 6% complete, structure (RCC) 5% complete, final finishes not started.
684 units booked out of total 3,839 units (18%).
Paradigm's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 9 |
|---|---|
| Total units across these projects | 5,095 |
| Completed without extending the possession date | 0 |
| Completed after an extension | 1 |
| Lapsed | 0 |
| Under construction | 8 |
| Possession date extended on the builder's application | 2 |
| MahaRERA complaints (filed by or against the builder), all Paradigm projects | 91 (5 of 9 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.