"Sale Bldg No. 6 (A & B) Wing Known As Northern Supremus & Northern Hills Building No. 1 & 2", Kandivali West

by N.Rose Developers Pvt Ltd · Kandivali West, Mumbai 400067 · Map

Launched
Apr 20197 yrs 8 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
100%Nearing possession
Booked
844 of 98586%
Buildings
21.3 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
670
3 BHK
212
Other units
103
Total units
985
Buildings
2
Land
1.3 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services45%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 59%Dec 2025: Concrete structure (RCC) 78%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 20%Dec 2025: Final finishes 60%Jul 2026: Final finishes 45%Excavation 100%Concrete structure (RCC) 100%Final finishes 45%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%45%844
100%78%60%785
100%59%20%638

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

"Sale Bldg No. 6 (A & B) Wing Known As Northern Supremus & Northern Hills Building No. 1 & 2" by N.Rose Developers Pvt Ltd is a 985-unit SRA-sanctioned project in Kandivali West, Mumbai 400067, launched in April 2019 with possession due in December 2026. 844 units booked out of total 985 units. The concrete structure (RCC) is complete.

Read full summary

"Sale Bldg No. 6 (A & B) Wing Known As Northern Supremus & Northern Hills Building No. 1 & 2" is an SRA-sanctioned project by N.Rose Developers Pvt Ltd in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800020350. It was launched in April 2019. It has 985 units in 2 buildings: 882 homes (2 and 3 BHK) and 103 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 45% complete.

844 units booked out of total 985 units (86%).