Alag Capital, Mulund West

by Alag Property Constructions Pvt Ltd · Mulund West, Mumbai 400080 · Map

Launched
May 20195 yrs 1 mth originally promised
Possession (MahaRERA)
Dec 2026Extended by 2 yrs 6 mths
Concrete structure
33%Mid-construction
Booked
41 of 6068%
Buildings
30.9 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
4
2 BHK
19
3 BHK
15
4 BHK
2
Other units
20
Total units
60
Buildings
3
Land
0.9 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)33%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 70%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 33%Jul 2026: Concrete structure (RCC) 33%Oct 2026: Concrete structure (RCC) 33%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 33%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%33%0%41
100%33%0%–
100%33%0%–
70%0%0%41

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Alag Capital by Alag Property Constructions Pvt Ltd is a 60-unit project in Mulund West, Mumbai 400080, launched in May 2019 with possession due in December 2026. 41 units booked out of total 60 units. The concrete structure (RCC) is 33% complete.

Read full summary

Alag Capital is a project by Alag Property Constructions Pvt Ltd in Mulund West, Mumbai 400080, registered with MahaRERA as P51800020773. It was launched in May 2019. It has 60 units in 3 buildings: 40 homes (1, 2, 3 and 4 BHK) and 20 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, extended by 2 years 6 months from the original June 2024. Construction: excavation complete, structure (RCC) 33% complete, final finishes not started.

41 units booked out of total 60 units (68%).