Ganesh Residency, Ghatkopar East
by Shree Venkateshwara Developers · Ghatkopar East, Mumbai 400077 · Map
- Launched
- May 20194 yrs 2 mths originally promised
- Possession (MahaRERA)
- Jul 2026Extended by 3 yrs
- Concrete structure
- 92%Mid-construction
- Booked (free sale)
- 3 of 1421% · 24 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale3 booked out of 14 units
Rehab24 units for existing members
Total 38 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 12
- 2 BHK
- 26
- Total units
- 38
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 14
- Rehab units
- 24
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 92% | 0% | 3 | |
| 100% | 92% | 0% | 3 | |
| 100% | 92% | 0% | – | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Ganesh Residency by Shree Venkateshwara Developers is a 38-unit BMC-sanctioned project in Ghatkopar East, Mumbai 400077, launched in May 2019 with possession due in July 2026. 3 units booked out of 14 units for sale. The concrete structure (RCC) is 92% complete.
Read full summary
Ganesh Residency is a BMC-sanctioned project by Shree Venkateshwara Developers in Ghatkopar East, Mumbai 400077, registered with MahaRERA as P51800021114. It was launched in May 2019. It has 38 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 38 units, 14 are for sale and 24 are rehab units for existing members.
Possession was due in July 2026, after an extension of 3 years from the original July 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 92% complete, final finishes not started.
3 units booked out of 14 units for sale (21%).