Priya Co-Operative Housing Society Ltd, Andheri West
by Arjunsingh Bhoorsingh Rathore · Andheri West, Mumbai 400058 · Map
- Launched
- Jun 20194 yrs originally promised
- Possession (MahaRERA)
- Jun 2027Extended by 4 yrs
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 3 of 1421% · 17 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 2Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale3 booked out of 14 units
Rehab17 units for existing members
Total 31 units. Rehab units are not for sale.
Project facts
- 1 RK
- 4
- 1 BHK
- 1
- 2 BHK
- 22
- 3 BHK
- 1
- Other units
- 3
- Total units
- 31
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 2
- Free-sale units
- 14
- Rehab units
- 17
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 3 | |
| 100% | 4% | 0% | – | |
| 100% | 4% | 0% | – | |
| 100% | 4% | 0% | 2 |
"–" means MahaRERA shows no figure for that update.
About this project
Priya Co-Operative Housing Society Ltd by Arjunsingh Bhoorsingh Rathore is a 31-unit BMC-sanctioned project in Andheri West, Mumbai 400058, launched in June 2019 with possession due in June 2027. 3 units booked out of 14 units for sale. The concrete structure (RCC) is complete.
Read full summary
Priya Co-Operative Housing Society Ltd is a BMC-sanctioned project by Arjunsingh Bhoorsingh Rathore in Andheri West, Mumbai 400058, registered with MahaRERA as P51800021193. It was launched in June 2019. It has 31 units in 1 building: 28 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 31 units, 14 are for sale and 17 are rehab units for existing members.
Its registered possession date is June 2027, extended by 4 years from the original June 2023. Construction: excavation complete, structure (RCC) complete, final finishes not started.
3 units booked out of 14 units for sale (21%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 4% to 100% and the possession date has moved from June 2024 to June 2027.