Satellite Elegance, Goregaon East
by Newone Constructions Private Limited · Goregaon East, Mumbai 400063 · Map
- Launched
- Aug 20195 yrs 4 mths originally promised
- Possession (MahaRERA)
- Apr 2027Extended by 2 yrs 4 mths
- Concrete structure
- 100%Nearing possession
- Booked
- 267 of 28793%
- Buildings
- 21.1 acres
- MahaRERA complaints
- 14Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 57
- 2 BHK
- 226
- 3 BHK
- 4
- Total units
- 287
- Buildings
- 2
- Land
- 1.1 acres
- Phases
- 1
- MahaRERA complaints
- 14
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 30% | 267 | |
| 100% | 100% | 30% | 267 | |
| 100% | 100% | 5% | 254 | |
| 100% | 98% | 0% | 239 |
"–" means MahaRERA shows no figure for that update.
About this project
Satellite Elegance by Newone Constructions Private Limited is a 287-unit SRA-sanctioned project in Goregaon East, Mumbai 400063, launched in August 2019 with possession due in April 2027. 267 units booked out of total 287 units. The concrete structure (RCC) is complete.
Read full summary
Satellite Elegance is an SRA-sanctioned project by Newone Constructions Private Limited in Goregaon East, Mumbai 400063, registered with MahaRERA as P51800021913. It was launched in August 2019. It has 287 units in 2 buildings, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is April 2027, extended by 2 years 4 months from the original December 2024. Construction: excavation complete, structure (RCC) complete, final finishes 30% complete.
267 units booked out of total 287 units (93%).