Chembur Shravan, Chembur

by John Dennis Constructions Pvt Ltd · Chembur, Mumbai 400071 · Map

Launched
Sep 20195 yrs originally promised
Possession (MahaRERA)
Apr 2027Extended by 2 yrs 7 mths
Concrete structure
57%Mid-construction
Booked (free sale)
54 of 54100% · 24 rehab units
Buildings
10.2 acres
MahaRERA complaints
2Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale54 booked out of 54 units

Rehab24 units for existing members

Total 78 units. Rehab units are not for sale.

Project facts

1 BHK
47
2 BHK
31
Total units
78
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
2
Free-sale units
54
Rehab units
24

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)57%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 90%Dec 2025: Excavation 95%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 50%Dec 2025: Concrete structure (RCC) 53%Jul 2026: Concrete structure (RCC) 57%Oct 2026: Concrete structure (RCC) 57%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 57%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%57%0%54
100%57%0%54
95%53%0%–
90%50%0%30

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Chembur Shravan by John Dennis Constructions Pvt Ltd is a 78-unit MHADA-sanctioned project in Chembur, Mumbai 400071, launched in September 2019 with possession due in April 2027. 54 units booked out of 54 units for sale. The concrete structure (RCC) is 57% complete.

Read full summary

Chembur Shravan is a MHADA-sanctioned project by John Dennis Constructions Pvt Ltd in Chembur, Mumbai 400071, registered with MahaRERA as P51800022435. It was launched in September 2019. It has 78 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 78 units, 54 are for sale and 24 are rehab units for existing members.

Its registered possession date is April 2027, extended by 2 years 7 months from the original September 2024. Construction: excavation complete, structure (RCC) 57% complete, final finishes not started.

54 units booked out of 54 units for sale (100%).