Chembur Shravan, Chembur
by John Dennis Constructions Pvt Ltd · Chembur, Mumbai 400071 · Map
- Launched
- Sep 20195 yrs originally promised
- Possession (MahaRERA)
- Apr 2027Extended by 2 yrs 7 mths
- Concrete structure
- 57%Mid-construction
- Booked (free sale)
- 54 of 54100% · 24 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 2Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale54 booked out of 54 units
Rehab24 units for existing members
Total 78 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 47
- 2 BHK
- 31
- Total units
- 78
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 2
- Free-sale units
- 54
- Rehab units
- 24
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 57% | 0% | 54 | |
| 100% | 57% | 0% | 54 | |
| 95% | 53% | 0% | – | |
| 90% | 50% | 0% | 30 |
"–" means MahaRERA shows no figure for that update.
About this project
Chembur Shravan by John Dennis Constructions Pvt Ltd is a 78-unit MHADA-sanctioned project in Chembur, Mumbai 400071, launched in September 2019 with possession due in April 2027. 54 units booked out of 54 units for sale. The concrete structure (RCC) is 57% complete.
Read full summary
Chembur Shravan is a MHADA-sanctioned project by John Dennis Constructions Pvt Ltd in Chembur, Mumbai 400071, registered with MahaRERA as P51800022435. It was launched in September 2019. It has 78 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 78 units, 54 are for sale and 24 are rehab units for existing members.
Its registered possession date is April 2027, extended by 2 years 7 months from the original September 2024. Construction: excavation complete, structure (RCC) 57% complete, final finishes not started.
54 units booked out of 54 units for sale (100%).