BKC Crown, Kurla West
by Shreeji Properties · Kurla West, Mumbai 400070 · Map
- Launched
- Dec 20197 yrs promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 100%Nearing possession
- Booked
- –
- Buildings
- 20.5 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 121
- 2 BHK
- 23
- 3 BHK
- 1
- Other units
- 6
- Total units
- 151
- Buildings
- 2
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 55% | – | |
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
BKC Crown by Shreeji Properties is a 151-unit SRA-sanctioned project in Kurla West, Mumbai 400070, launched in December 2019 with possession due in December 2026. The concrete structure (RCC) is complete.
Read full summary
BKC Crown is an SRA-sanctioned project by Shreeji Properties in Kurla West, Mumbai 400070, registered with MahaRERA as P51800023174. It was launched in December 2019. It has 151 units in 2 buildings: 145 homes (1, 2 and 3 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 55% complete.
Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 100%.