Rakshi-Elanza, Andheri East
by Om Sai Builders & Developers · Andheri East, Mumbai 400099 · Map
- Launched
- Dec 20197 yrs 3 mths promised
- Possession (MahaRERA)
- Mar 2027Not extended
- Concrete structure
- 100%Nearing possession
- Booked
- 62 of 15440%
- Buildings
- 11.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 60
- 2 BHK
- 83
- 3 BHK
- 11
- Total units
- 154
- Buildings
- 1
- Land
- 1.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 70% | 62 | |
| 100% | 100% | 70% | – | |
| 100% | 100% | 70% | – | |
| 100% | 100% | 70% | 62 |
"–" means MahaRERA shows no figure for that update.
About this project
Rakshi-Elanza by Om Sai Builders & Developers is a 154-unit project in Andheri East, Mumbai 400099, launched in December 2019 with possession due in March 2027. 62 units booked out of total 154 units. The concrete structure (RCC) is complete.
Read full summary
Rakshi-Elanza is a project by Om Sai Builders & Developers in Andheri East, Mumbai 400099, registered with MahaRERA as P51800023224. It was launched in December 2019. It has 154 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is March 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 70% complete.
62 units booked out of total 154 units (40%).