Kuber Heights, Mulund East
by United Construction Co · Mulund East, Mumbai 400081 · Map
- Launched
- Dec 20195 yrs originally promised
- Possession (MahaRERA)
- Apr 2028Extended by 3 yrs 4 mths
- Concrete structure
- 100%Nearing possession
- Booked
- 113 of 13683% · 108 in Jul 2026
- Buildings
- 20.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 90
- 2 BHK
- 46
- Total units
- 136
- Buildings
- 2
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 13% | 113 | |
| 100% | 100% | 13% | 108 | |
| 100% | 89% | 10% | 106 | |
| 100% | 19% | 0% | 39 |
"–" means MahaRERA shows no figure for that update.
About this project
Kuber Heights by United Construction Co is a 136-unit SRA-sanctioned project in Mulund East, Mumbai 400081, launched in December 2019 with possession due in April 2028. 113 units booked out of total 136 units. The concrete structure (RCC) is complete.
Read full summary
Kuber Heights is an SRA-sanctioned project by United Construction Co in Mulund East, Mumbai 400081, registered with MahaRERA as P51800023657. It was launched in December 2019. It has 136 units in 2 buildings, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is April 2028, extended by 3 years 4 months from the original December 2024. Construction: excavation complete, structure (RCC) complete, final finishes 13% complete.
113 units booked out of total 136 units (83%). Since the July 2026 update, 5 more units have been booked and the possession date has moved from December 2025 to April 2028.