M K Residency, Kurla West

by Shaista Majid Khan · Kurla West, Mumbai 400070 · Map

Launched
Jan 20203 yrs 11 mths originally promised
Possession (MahaRERA)
Dec 2024Extended by 1 yr
Concrete structure
95%Mid-construction
Booked
–
Buildings
10.7 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
1
1 BHK
106
2 BHK
3
Other units
40
Total units
150
Buildings
1
Land
0.7 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)95%
Finishes, lifts and services92%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 95%Jul 2026: Concrete structure (RCC) 95%Dec 2024: Final finishes 90%Dec 2025: Final finishes 92%Jul 2026: Final finishes 92%Excavation 100%Concrete structure (RCC) 95%Final finishes 92%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%95%92%–
100%95%92%–
100%100%90%128

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

M K Residency by Shaista Majid Khan is a 150-unit project in Kurla West, Mumbai 400070, launched in January 2020 with possession due in December 2024. The concrete structure (RCC) is 95% complete.

Read full summary

M K Residency is a project by Shaista Majid Khan in Kurla West, Mumbai 400070, registered with MahaRERA as P51800023938. It was launched in January 2020. It has 150 units in 1 building: 110 homes (1 RK, 1 BHK and 2 BHK) and 40 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Possession was due in December 2024, after an extension of 1 year from the original December 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 95% complete, final finishes 92% complete.