Pushpanjali Residency, Vikhroli
by Shree Dham Developers · Vikhroli, Mumbai 400083 · Map
- Launched
- Jan 20203 yrs 11 mths originally promised
- Possession (MahaRERA)
- Oct 2027Extended by 3 yrs 10 mths
- Concrete structure
- 86%Mid-construction
- Booked (free sale)
- 84 of 9886% · 32 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale84 booked out of 98 units
Rehab32 units for existing members
Total 130 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 75
- 2 BHK
- 45
- Other units
- 10
- Total units
- 130
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 98
- Rehab units
- 32
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 86% | 10% | 84 | |
| 100% | 86% | 10% | 84 | |
| 100% | 86% | 0% | 84 | |
| 80% | 86% | 0% | 48 |
"–" means MahaRERA shows no figure for that update.
About this project
Pushpanjali Residency by Shree Dham Developers is a 130-unit MHADA-sanctioned project in Vikhroli, Mumbai 400083, launched in January 2020 with possession due in October 2027. 84 units booked out of 98 units for sale. The concrete structure (RCC) is 86% complete.
Read full summary
Pushpanjali Residency is a MHADA-sanctioned project by Shree Dham Developers in Vikhroli, Mumbai 400083, registered with MahaRERA as P51800024049. It was launched in January 2020. It has 130 units in 1 building: 120 homes (1 and 2 BHK) and 10 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 130 units, 98 are for sale and 32 are rehab units for existing members.
Its registered possession date is October 2027, extended by 3 years 10 months from the original December 2023. Construction: excavation complete, structure (RCC) 86% complete, final finishes 10% complete.
84 units booked out of 98 units for sale (86%).