Vraj Bhumi Heights, Jogeshwari East
by Landmark Heights Private Limited · Jogeshwari East, Mumbai 400060 · Map
- Launched
- Feb 20205 yrs 10 mths originally promised
- Possession (MahaRERA)
- Dec 2028Extended by 3 yrs
- Concrete structure
- 75%Mid-construction
- Booked (free sale)
- 17 of 4935% · 10 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 2Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale17 booked out of 49 units
Rehab10 units for existing members
Total 59 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 55
- Other units
- 4
- Total units
- 59
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 2
- Free-sale units
- 49
- Rehab units
- 10
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 75% | 0% | 17 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Vraj Bhumi Heights by Landmark Heights Private Limited is a 59-unit BMC-sanctioned project in Jogeshwari East, Mumbai 400060, launched in February 2020 with possession due in December 2028. 17 units booked out of 49 units for sale. The concrete structure (RCC) is 75% complete.
Read full summary
Vraj Bhumi Heights is a BMC-sanctioned project by Landmark Heights Private Limited in Jogeshwari East, Mumbai 400060, registered with MahaRERA as P51800024289. It was launched in February 2020. It has 59 units in 1 building: 55 homes (1 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 59 units, 49 are for sale and 10 are rehab units for existing members.
Its registered possession date is December 2028, extended by 3 years from the original December 2025. Construction: excavation complete, structure (RCC) 75% complete, final finishes not started.
17 units booked out of 49 units for sale (35%). Since the December 2024 update, 17 more units have been booked, the reported concrete structure (RCC) has gone from 0% to 75% and the possession date has moved from December 2025 to December 2028.