Safal Ganga Smruti, Chembur

by Varun Homes Pvt Ltd · Chembur, Mumbai 400074 · Map

Launched
Feb 20204 yrs 1 mth originally promised
Possession (MahaRERA)
Nov 2026Extended by 2 yrs 8 mths
Concrete structure
61%Mid-construction
Booked (free sale)
35 of 4185% · 22 rehab units
Buildings
10.3 acres
MahaRERA complaints
3Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale35 booked out of 41 units

Rehab22 units for existing members

Total 63 units. Rehab units are not for sale.

Project facts

1 BHK
30
2 BHK
33
Total units
63
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
3
Free-sale units
41
Rehab units
22

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)61%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 61%Dec 2025: Concrete structure (RCC) 61%Jul 2026: Concrete structure (RCC) 61%Oct 2026: Concrete structure (RCC) 61%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 61%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%61%0%35
100%61%0%35
100%61%0%33
100%61%0%12

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Safal Ganga Smruti by Varun Homes Pvt Ltd is a 63-unit BMC-sanctioned project in Chembur, Mumbai 400074, launched in February 2020 with possession due in November 2026. 35 units booked out of 41 units for sale. The concrete structure (RCC) is 61% complete.

Read full summary

Safal Ganga Smruti is a BMC-sanctioned project by Varun Homes Pvt Ltd in Chembur, Mumbai 400074, registered with MahaRERA as P51800024417. It was launched in February 2020. It has 63 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 63 units, 41 are for sale and 22 are rehab units for existing members.

Its registered possession date is November 2026, extended by 2 years 8 months from the original March 2024. Construction: excavation complete, structure (RCC) 61% complete, final finishes not started.

35 units booked out of 41 units for sale (85%).