Safal Ganga Smruti, Chembur
by Varun Homes Pvt Ltd · Chembur, Mumbai 400074 · Map
- Launched
- Feb 20204 yrs 1 mth originally promised
- Possession (MahaRERA)
- Nov 2026Extended by 2 yrs 8 mths
- Concrete structure
- 61%Mid-construction
- Booked (free sale)
- 35 of 4185% · 22 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 3Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale35 booked out of 41 units
Rehab22 units for existing members
Total 63 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 30
- 2 BHK
- 33
- Total units
- 63
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 3
- Free-sale units
- 41
- Rehab units
- 22
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 61% | 0% | 35 | |
| 100% | 61% | 0% | 35 | |
| 100% | 61% | 0% | 33 | |
| 100% | 61% | 0% | 12 |
"–" means MahaRERA shows no figure for that update.
About this project
Safal Ganga Smruti by Varun Homes Pvt Ltd is a 63-unit BMC-sanctioned project in Chembur, Mumbai 400074, launched in February 2020 with possession due in November 2026. 35 units booked out of 41 units for sale. The concrete structure (RCC) is 61% complete.
Read full summary
Safal Ganga Smruti is a BMC-sanctioned project by Varun Homes Pvt Ltd in Chembur, Mumbai 400074, registered with MahaRERA as P51800024417. It was launched in February 2020. It has 63 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 63 units, 41 are for sale and 22 are rehab units for existing members.
Its registered possession date is November 2026, extended by 2 years 8 months from the original March 2024. Construction: excavation complete, structure (RCC) 61% complete, final finishes not started.
35 units booked out of 41 units for sale (85%).