M R Infrastructure And Developers, Khar West

by M. R. Infrastructure & Developers · Khar West, Mumbai 400052 · Map

Launched
Mar 20203 yrs originally promised
Possession (MahaRERA)
Dec 2026Extended by 3 yrs 9 mths
Concrete structure
100%Nearing possession
Booked
–
Buildings
20.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
18
Total units
18
Buildings
2
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%–
100%100%0%–
100%100%0%–
100%100%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

M R Infrastructure And Developers by M. R. Infrastructure & Developers is an 18-unit project in Khar West, Mumbai 400052, launched in March 2020 with possession due in December 2026. The concrete structure (RCC) is complete.

Read full summary

M R Infrastructure And Developers is a project by M. R. Infrastructure & Developers in Khar West, Mumbai 400052, registered with MahaRERA as P51800024803. It was launched in March 2020. It has 18 units in 2 buildings, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, extended by 3 years 9 months from the original March 2023. Construction: excavation complete, structure (RCC) complete, final finishes not started.