The X Ghatkopar, Vikhroli

by Arihant Realtors · Vikhroli, Mumbai 400079 · Map

Launched
Mar 20206 yrs 9 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
0%Early stage
Booked
62 of 20830%
Buildings
10.6 acres
MahaRERA complaints
12Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
1
2 BHK
44
3 BHK
33
4 BHK
22
Other units
108
Total units
208
Buildings
1
Land
0.6 acres
Phases
1
MahaRERA complaints
12

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 80%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%62
100%0%0%–
100%0%0%–
80%0%0%62

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

The X Ghatkopar by Arihant Realtors is a 208-unit project in Vikhroli, Mumbai 400079, launched in March 2020 with possession due in December 2026. 62 units booked out of total 208 units. Work on the concrete structure (RCC) has not started.

Read full summary

The X Ghatkopar is a project by Arihant Realtors in Vikhroli, Mumbai 400079, registered with MahaRERA as P51800025235. It was launched in March 2020. It has 208 units in 1 building: 100 homes (1, 2, 3 and 4 BHK) and 108 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

62 units booked out of total 208 units (30%).