Arihant Niwara Sky, Sion
by Dream Arihant Infrastructure Company · Sion, Mumbai 400022 · Map
- Launched
- May 20205 yrs originally promised
- Possession (MahaRERA)
- May 2027Extended by 2 yrs
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 101 of 11588% · 44 rehab units
- Buildings
- 10.5 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale101 booked out of 115 units
Rehab44 units for existing members
Total 159 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 46
- 2 BHK
- 67
- 3 BHK
- 46
- Total units
- 159
- Buildings
- 1
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 115
- Rehab units
- 44
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 50% | 101 | |
| 100% | 95% | 40% | 95 | |
| 100% | 80% | 0% | 87 | |
| 100% | 60% | 0% | 20 |
"–" means MahaRERA shows no figure for that update.
About this project
Arihant Niwara Sky by Dream Arihant Infrastructure Company is a 159-unit MHADA-sanctioned project in Sion, Mumbai 400022, launched in May 2020 with possession due in May 2027. 101 units booked out of 115 units for sale. The concrete structure (RCC) is complete.
Read full summary
Arihant Niwara Sky is a MHADA-sanctioned project by Dream Arihant Infrastructure Company in Sion, Mumbai 400022, registered with MahaRERA as P51800025450. It was launched in May 2020. It has 159 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 159 units, 115 are for sale and 44 are rehab units for existing members.
Its registered possession date is May 2027, extended by 2 years from the original May 2025. Construction: excavation complete, structure (RCC) complete, final finishes 50% complete.
101 units booked out of 115 units for sale (88%). Since the July 2026 update, 6 more units have been booked, the reported concrete structure (RCC) has gone from 95% to 100% and the possession date has moved from May 2026 to May 2027.